Retail · Five stores · England

Supporting a major UK retailer build one new store a week in 2025

A design and build contractor delivering new stores for a major UK food retailer needed M&E design to match a programme of one new store a week. In 2025 we designed five of them, each taken from first issue to construction issue in five to nine weeks.

The stores

The retailer has a well-developed standard for its stores, but each site is different: incoming supplies, drainage routes, roof plant positions, car parks and planning conditions all change. The design follows the standard and adapts it to the site.

Design programme

For each store we produced the full M&E design: heating and cooling, ventilation and ductwork, domestic water and drainage, lighting including the car park, small power, EV charging supplies, and the supporting calculations. These included psychrometric checks on the cooling, hot and mains water sizing, water hardness, cable sizing and protective device settings.

Drawings were issued to the contractor's design release programme, in the order the trades needed them, starting with builder's work. Each store went from first issue to construction issue in five to nine weeks.

Construction stage

During construction we revised layouts as the contractor's supply chain was confirmed, kept a variation schedule, updated the BREEAM water information and answered site queries, through to as-fitted drawings.

5New stores designed in 2025
5–9 wksFirst issue to construction issue
50+Drawing issues across the programme
MEPFull mechanical, electrical and public health scope
Contact

Talk to us about a project

Tell us about the building, the problem and the programme. We reply within one working day with whether we can help, what it would cost and what we would need from you.